Daily Activities

UPSC Prelims Current Affairs

UPSC Mains Current Affairs

Current Affairs

Kiru Hydroelectric Project Chenab Valley Progress

Kiru Hydroelectric Project Chenab Valley Progress

As of 24 June 2026 the 624 MW Kiru Hydroelectric Power Project in Kishtwar (Chenab Valley) has recorded 83.46% physical progress and targets commissioning in December 2026.

Project Snapshot

  • Capacity & Type: 624 MW run‑of‑river; annual generation ~2,272 million units (MU).
  • Location: Kishtwar district, Chenab basin, Jammu & Kashmir.
  • Progress & Expenditure: 83.46% physical progress; cumulative expenditure Rs 3,733.26 crore (as on 24 Jun 2026).
  • Commissioning: Targeted December 2026; original dates: Sep 2023 → Jul 2025 → Dec 2026 (≈39 months overall delay).

Cost, Approvals & Causes of Delay

  • Original sanction: Jan 2022 at Rs 4,287.59 crore.
  • Revised cost: Rs 5,409 crore; increase ≈ Rs 1,121.41 crore.
  • Delay factors: geological complexity, difficult mountainous terrain, adverse weather and logistics in Chenab Valley.

Technical Features

  • Dam & Works: 135 m concrete gravity dam, diversion tunnels and pressure shafts.
  • Powerhouse & Turbines: Underground powerhouse with four 156 MW vertical Francis turbines.
  • Generation unit: Annual output expressed in MU (1 MU = 1 million kWh).

Institutional & Basin Linkages

  • Developer: Chenab Valley Power Projects Pvt Ltd (CVPPPL), JV: NHPC 51% — JKSPDC 49%.
  • Programme linkage: Part of Chenab basin hydroelectric development programme.

IASPOINT Booster Facts

  • NHPC: Central public sector enterprise under the Ministry of Power focused on hydroelectric projects.
  • Francis turbine: Common for medium‑head schemes; suitable for heads from ~10 m to several hundred metres.
Last Modified: June 27, 2026

Leave a Reply

Your email address will not be published. Required fields are marked *

Archives